ਵਿਵਾਦ ਨਿਪਟਾਰਾ ਕੇਸ

ਵਿਵਾਦ ਨਿਪਟਾਰਾ ਕੇਸ

ਕੇਸ ਹਵਾਲਾ ਨੰਬਰ :
ਕੇਸ ਹਵਾਲਾ ਨੰਬਰ: R1552
1.  ਕੇਸ ਹਵਾਲਾ ਨੰਬਰ R1552
1.  ਉੱਪ ਮੰਡਲ ਦਫਤਰ CITY WEST LUDHIANA/DS ESTATE (SPL) DIVN./COMM. ESTATE (SPL)
2.  ਖਪਤਕਾਰ Sl040131 of Sh/ Ms Geetech Eng. P.Ltd
3.  ਕੇਸ ਦਾਖਲ ਕਰਨ ਦੀ ਮਿਤੀ 2012-10-01
4.  ਵਰਨਣ Weekly Off Day
5.  ਫੈਸਲਾ Brief History: The petitioner is having LS connection bearing account no SL 04/131 in the name M/s Gee Tech with sanctioned load of 485.00KW. The DDL of the meter was taken on dt 20.12.11 and 1.3.12 and the consumer was found violating PLV and WOD. The consumer was charged Rs.39387/- as PLV and Rs.230420/- as WOD. The consumer was not satisfied with the amount raised on him and requested the office of CE/DS Central Zone Ludhiana for review of his case in ZDSC. On the request of the consumer, the case was registered for hearing vide CE/DS Central memo no 10346/48 dated 1.10.2012. ZDSC heard this case on 26.10.2012, 16.11.12, 3.12.12, 3.1.2013, 2.2.2013 and finally on dated 22.2.2013 when the case was closed for passing speaking order. The petitioner submitted his petition on dt 26.10.12 in which he contested that the amount charged to him is not correct. He stated that MMTS department has charged the WOD amount by treating his industry as Furnace where as furnace industry was started on 11.09.2012. As such he should be charged the WOD charges by treating his industries as general industry. M/s GeeTech Engineers (P) Ltd. A/c No.SL04/0131 PO submitted parawise reply of the consumer’s petition. PO in his reply has made clear that the amount charged to the consumer by MMTS is treating his industry as furnace. He further stated that the connection of the consumer was checked by Enforcement MMTS and Operation Staff on dated 23.07.2011 and reported that the consumer was using furnace by tapping 11 KV incoming cable and connection was disconnection on 24.7.2011. After the direction of Hon’ble court his connection was re-connected in the month 10/2011. The Load of furnace i.e. 250KVA and General Load i.e. 245KVA was sanctioned on 11.09.2012. Earlier the consumer was charged WOD amount on basis of furnace load by MMTS-III Ludhiana. In the meeting held on 3.12.12, the committed directed to PO to submit consumption data for 3 years, sanctioned load, calculation sheet and the amount charged to the consumer may be got verified from the MMTS. The case was referred to Addl.SE/MMTS-3, Ludhiana vide Dice/West Circle, Ludhiana vide his office memo.No.1036/37 dated 29.1.2013. Sr. Xen , MMTS -3,Ludhiana vide his office memo.No.1262 dated 30.1.2013 has made cleared that in reference to Joint checking of Enforcement the subject cited consumer was running Induction Furnace. So consumer was considered PIU Unit and charged as per CC 89/95 and Electricity Supply Reg(Amended up to 31.12.2004)clause No.168.1.1. Observation of the committee: - During arguments the PO informed the committee that the petitioner was cought steeling energy during joint checking by Enforcement and Operation staff on 23.7.11 and provisional notice of assessment was served upon the consumer which was reviewed by the designated authority comprising of CE/DS and CE/Enforcement jointly and during course of review on perusal of record and investigation the designated authority passed the speaking orders vide Memo No 11302 dt. 25.8.11 in which it was clearly concluded that the petitioner is using power intensive load in his premises after 5.5.2011. The relevant portion of speaking oder is reproduced as follows: M/s GeeTech Engineers (P) Ltd. A/c No.SL04/0131 M/s GeeTech Engineers (P) Ltd. A/c No.SL04/0131 Decision of the committee: - Based upon above discussion the committee decided that the amount charged to the petitioner on account of WOD/PLV considering him as PIU is correct and recoverable. The balance amount recoverable / refundable, be recovered / refunded from / to the petitioner alongwith interest / surcharge as per instructions of PSPCL.
6.  ਫੈਸਲੇ ਦੀ ਮਿਤੀ 2013-02-22
ਸੁਣਵਾਈ/ ਪੇਸ਼ੀਆਂ
Page 1/1
 
Sr Noਸੁਣਵਾਈ ਦੀ ਮਿਤੀਵਰਨਣ
1 Fri 16, Nov 2012  Sh. Deepak Kumar appeared before the committee and submitted petition which was handed over to PO. He was directed to give point wise reply of the petition and also submit consumption of last three years which includes KWAH KVAH and MDI readings. Case is deferred.