| 1. |
ਕੇਸ ਹਵਾਲਾ ਨੰਬਰ |
Q2346
|
| 1. |
ਉੱਪ ਮੰਡਲ ਦਫਤਰ |
SUB URBAN LUDHIANA/DS S/U DIVN. LALTON KALAN/DS S/D NARANGWAL
|
| 2. |
ਖਪਤਕਾਰ |
U43RV983 of Sh/ Ms Harcharan S.Kila Rai
|
| 3. |
ਕੇਸ ਦਾਖਲ ਕਰਨ ਦੀ ਮਿਤੀ |
2012-08-31
|
| 4. |
ਵਰਨਣ |
This AP connection was checked by Enforcement. The connected load was found 17.5 BHP against the sanctioned load of 10 BHP.
|
| 5. |
ਫੈਸਲਾ |
The consumer produced the copy of cash memo of 12.5 BHP motor and SDO Narangwal physically varified the motor. So decided that the charged amount may be revised by taking the motor as 12.5 BHP.
|
| 6. |
ਫੈਸਲੇ ਦੀ ਮਿਤੀ |
2013-03-14
|
| ਸੁਣਵਾਈ/ ਪੇਸ਼ੀਆਂ |
Page 1/1 |
|---|
| Sr No | ਸੁਣਵਾਈ ਦੀ ਮਿਤੀ | ਵਰਨਣ |
| 1 | Fri 11, Jan 2013 |
The consumer informed that he has purchased the motor of LUBI make in 5/2012 whose particulars are written on the bill and he will produce the bill before the committee in the next meeting. The case is deferred. |
| |