| 1. |
ਕੇਸ ਹਵਾਲਾ ਨੰਬਰ |
U3450
|
| 1. |
ਉੱਪ ਮੰਡਲ ਦਫਤਰ |
GURDASPUR/DS S/U DIVN. PATHANKOT/DS S/D DHAR
|
| 2. |
ਖਪਤਕਾਰ |
GC61/0027 of Sh/ Ms Boys Hostel Sai Coll
|
| 3. |
ਕੇਸ ਦਾਖਲ ਕਰਨ ਦੀ ਮਿਤੀ |
2014-02-24
|
| 4. |
ਵਰਨਣ |
The consumer has extending load of A/C. no. SF30/1480 from 19.830 KW to 97.410 KW, SDO Dhar allotted the new A/C. No. GC61/0027 against extending load. But his old A/C No. has not been disconnected in the papers. Resulted which billing of both A/C nos. has been issued, which was challenged by the consumer in the Circle level DSC.
|
| 5. |
ਫੈਸਲਾ |
It was decided by the committee that consumer has not used total sanctioned load of account no. GC61/0027. The bill charged against A/c. No. SF30/1400 with effect of 20-10-2012 not recoverable as the same connection has emerged against new A/C no. GC61/0027 due to extension of load.
|
| 6. |
ਫੈਸਲੇ ਦੀ ਮਿਤੀ |
2014-06-30
|
| ਸੁਣਵਾਈ/ ਪੇਸ਼ੀਆਂ |
Page 1/1 |
|---|
| Sr No | ਸੁਣਵਾਈ ਦੀ ਮਿਤੀ | ਵਰਨਣ |
| 1 | Mon 30, Jun 2014 |
The representative Sh. R.N.Sharma CAO presented before the DSC committee. on dated 30-6-2014. |
| |