Real-time Status Report
Sr. No.Name of ServiceTime Limit prescribed as per the Public Service Guarantee Act or Equivalent Act Total Number of Applications receivedTotal Number of Applications Processed Average time taken to grant approval in DaysMedian in DaysMinimum in Days Maximum in Days
1. New Connection - With Augumentation - LT Within 30 days 2971 2948 11.00 7.31 0.00 93.60
2. New Connection - With Augumentation - HT 11KV Within 49 days 22 21 1.34 0.01 0.00 20.02
3. New Connection - With Augumentation - EHT Within 90 days 4 3 0.09 0.06 0.06 0.11
4. Temporary Connection Within 15 days 1252 1242 1.94 0.04 0.00 35.67
5. New Connection - Without Augumentation - DS/NRS Within 7 days 8663 8583 5.24 0.00 0.00 106.09
6. New Connection - Without Augumentation - other than DS/NRS Within 15 days 71 68 2.39 10.85 0.00 42.98
7. New Connection - With Augumentation - HT 33KV Within 75 days 5 4 0.11 0.11 0.03 0.20